The Changheba Dam (simplified Chinese: 长河坝水电站; traditional Chinese: 長河壩水電站) is a concrete rock-filled embankment dam across the Dadu River near Kangding in Sichuan Province, China. The dam was built for the purpose of generating hydroelectricity.
| Changheba Dam | |
|---|---|
A 200 m-high (660 ft) road bridge over the reservoir, in 2015 | |
Location of the dam in Sichuan | |
![]() Interactive map of Changheba Dam | |
| Country | China |
| Location | Kangding, Sichuan |
| Coordinates | 30°08′56″N 102°10′27″E / 30.148840°N 102.174243°E |
| Purpose | Power |
| Status | Operational |
| Construction began | 2006 |
| Opening date | 2017 |
| Construction cost | US$3.46 billion |
| Owner | Datang International Sichuan Power Generation Co Ltd |
| Dam and spillways | |
| Type of dam | Rock-fill dam |
| Impounds | Dadu River |
| Height | 240 m (790 ft) |
| Length | 1,697 m (5,568 ft) |
| Reservoir | |
| Creates | Changheba Reservoir |
| Total capacity | 1,075 GL (872,000 acre⋅ft) |
| Changheba hydroelectric plant (Chinese: 长河坝水电站) | |
| Coordinates | 30°24′11″N 102°07′17″E / 30.4031°N 102.1213°E |
| Operator | Sichuan Datang International Ganzi Hydropower Development |
| Commission date | 2017 |
| Type | Conventional |
| Turbines | 4 x 650 MW (870×103 hp) (all Francis-type) |
| Installed capacity | 2,600 MW (3.5×106 hp) |
| [1] | |
Overview
editConstruction of the concrete-faced rock-filled dam began in 2006, before it was officially approved in December 2010 and impounded in 2016. The power station was fully operational in December 2017.[2][a]
The dam wall is 240 metres (790 ft) high and 1,697 metres (5,568 ft) long. When full, the resultant reservoir, has a capacity of 1,075 gigalitres (872,000 acre⋅ft).[4][5] In July 2009, a landslide at the construction site killed four people while causing damage and temporarily blocking the river.[6]
See also
editNotes
editReferences
edit- ↑ "Changheba hydroelectric plant". Global Energy Monitor. March 18, 2026. Retrieved April 12, 2026.
- ↑ "Changheba Hydropower Approved". Breakbulk. November 18, 2010. Archived from the original on March 6, 2012. Retrieved January 9, 2011.
- ↑ "Changheba Dam". structurae.net. 2026. Retrieved April 12, 2026.
- ↑ "China's largest Hydropower installed Capacity Dams". Chinese National Committee on Large Dams. July 12, 2010. Retrieved January 9, 2011.
- ↑ "Changheba hydropower station all put into operation" (in Simplified Chinese). Power China. December 4, 2017. Archived from the original on December 25, 2018. Retrieved January 16, 2018.
- ↑ "China: 4 Die as Landslide Destroys Dam Project". The New York Times. Reuters. July 24, 2009. Retrieved January 9, 2011.
External links
edit- Xu, Hao; Haibo, Li; Yang, Xingguo; Qi, Shunchao; Zhou, Jiawen (2018). "Integration of Terrestrial Laser Scanning and NURBS Modeling for the Deformation Monitoring of an Earth-Rock Dam". Sensors. 19 (22): 22. Bibcode:2018Senso..19...22X. doi:10.3390/s19010022. PMC 6339106. PMID 30577647.
- LI, Shu-yong; LI, Hai-bo; HAN, Xing; HOU, Qi-dong; YANG, Xing-guo (2018). "Field compaction tests on rockfill dams based on surface settlement method". Chinese Journal of Geotechnical Engineering. 40 (S2): 127–131. doi:10.11779/CJGE2018S2026.